The Study of Risk Management of MRT Project in Construction Stage – The Owner’s Perspective

Date Issued
2010
Date
2010
Author(s)
Hsieh, Yung-Chang
URI
http://ntur.lib.ntu.edu.tw//handle/246246/256195
Abstract
A Mass Rapid Transit (MRT) system retains critical influences on the development of metropolis. The government has invested a large fund in the MRT construction for years in order to solve the over-demands in metropolis. Since the systematic project of MRT has properties, such as great scale, high cost, long duration, complicated interface relation, technological degree of high difficulty, etc. There are a lot of uncertain factors in the course of construction which cause the project unable to finish by schedule and qualified within the budget. These factors are not only hard to reveal the benefits of the MRT timely but also having profound effects on government''s administrative results. In order to reduce the risk resulting from the budget which might be out of control and delay, this research is made through typical risk management procedures, including risk identification, risk assessment and analysis, risk response, etc. Regarding the MRT’s civil and architecture engineering project handled by the government’s department, this research objects by means of advises from 8 specialists and scholars, who have experienced or engaged in construction, construction management or engineering planning and detailed design for many years and have participated in and performed the MRT project. It puts themselves in the Owner’s position to think over the Owner’s needs, to propose the risk factors related to the Owner during the engineering construction stages and to establish a risk checklist for this research; it proceeds to assess the possibility of the risk factors along with the influential level of impacts by the visiting specialists and scholars. They use the results assessed as a decision basis for the follow-up risks’ responses which are subject to the importance and priority. Finally, consulting the specialists and scholars to offer three types of risk factors, including higher possibility of the risk, larger influential level of impacts and higher risk value, with corresponding tactics and measures. The result of this research gathered a total of 34 items of risk factors of Owner’s possibility that would occur is found to be relatively low, whereas the influential level of impact is relatively high during the civil and architecture engineering of the MRT construction stage. Among them, the risk factor with supreme possibility would occur is “the interface problem of the civil and mechanical engineering”, and there are two items of the risk factors with uppermost influential level of impact. One is “the milestone overdue caused the correlated manufacturers to delay in entering the site”, and the other is “the manufacturer has got into trouble in financial difficulties or folded up”. Besides, the first three risk factors with highest risk value are “the milestone overdue caused the correlated manufacturers to delay in entering the site”, “the interface problem of the civil and mechanical engineering” and “relocation of the underground pipeline”. The properties of the risk factors mentioned above are consistent. Furthermore, this research concluded the results by means of visiting the specialists and considered the tactics and measures of the Owner’s responses during civil and architecture engineering of the MRT project construction stage. They rely mainly on preventing and reducing, even though some of the risks can be transferred without insurance, but the majority may have the possibility to be retained and solved by Owner.
Subjects
Risk
Risk Management
Mass Rapid Transit (MRT) project
Construction
Construction Stage
Owner
File(s)
Loading...
Thumbnail Image
Name

ntu-99-P96521703-1.pdf

Size

23.32 KB

Format

Adobe PDF

Checksum

(MD5):1da2b661d4ef78f4a2aecae4c4dc6284

臺大位居世界頂尖大學之列,為永久珍藏及向國際展現本校豐碩的研究成果及學術能量,圖書館整合機構典藏(NTUR)與學術庫(AH)不同功能平台,成為臺大學術典藏NTU scholars。期能整合研究能量、促進交流合作、保存學術產出、推廣研究成果。

To permanently archive and promote researcher profiles and scholarly works, Library integrates the services of “NTU Repository” with “Academic Hub” to form NTU Scholars.

總館學科館員 (Main Library)
醫學圖書館學科館員 (Medical Library)
社會科學院辜振甫紀念圖書館學科館員 (Social Sciences Library)

開放取用是從使用者角度提升資訊取用性的社會運動,應用在學術研究上是透過將研究著作公開供使用者自由取閱,以促進學術傳播及因應期刊訂購費用逐年攀升。同時可加速研究發展、提升研究影響力,NTU Scholars即為本校的開放取用典藏(OA Archive)平台。(點選深入了解OA)

  • 請確認所上傳的全文是原創的內容,若該文件包含部分內容的版權非匯入者所有,或由第三方贊助與合作完成,請確認該版權所有者及第三方同意提供此授權。
    Please represent that the submission is your original work, and that you have the right to grant the rights to upload.
  • 若欲上傳已出版的全文電子檔,可使用Open policy finder網站查詢,以確認出版單位之版權政策。
    Please use Open policy finder to find a summary of permissions that are normally given as part of each publisher's copyright transfer agreement.
  • 網站簡介 (Quickstart Guide)
  • 使用手冊 (Instruction Manual)
  • 線上預約服務 (Booking Service)
  • 方案一:臺灣大學計算機中心帳號登入
    (With C&INC Email Account)
  • 方案二:ORCID帳號登入 (With ORCID)
  • 方案一:定期更新ORCID者,以ID匯入 (Search for identifier (ORCID))
  • 方案二:自行建檔 (Default mode Submission)
  • 方案三:學科館員協助匯入 (Email worklist to subject librarians)

Built with DSpace-CRIS software - Extension maintained and optimized by 4Science