  4. The Effect of Monsoon on Schedule Planning for Wind Generator Construction in Penghu Wind Farm
 
  • Details

The Effect of Monsoon on Schedule Planning for Wind Generator Construction in Penghu Wind Farm

Date Issued
2011
Date
2011
Author(s)
Lian, Ryh-Shin
URI
http://ntur.lib.ntu.edu.tw//handle/246246/255670
Abstract
Abstract There is a shortage of energy source in Taiwan, and need to import energy more than 98% from oversea. Therefore, the decrease of imported energy source is a major topic in Taiwan. Wind generating is clean with renewable energy, so there are character in low pollution and cost down, inexhaustible in supply and always available for use. Taiwan is an oceanic island, there are northeast monsoon over 6 months annually and southwest monsoon in summer, therefore wind velocity reach 4 m/s average in total area over 2,000 square kilometers, the wind energy source is rich. The wind energy source in the Penghu Island has been investigated and analyzed, whose capacity factor 45 % is the best in global, so that government positive develop wind generator set nearly. From 1999, Taiwan Power Company have established wind generator amount 162 set with total capacity 288.76 MW for commercial operation, Independent Power Producer have established amount 114 set with total capacity 254.05 MW, up to now. Taiwan’s west coast have been almost developed relating optimum wind farm. In 2011, government declared Low Carbon Island Plan for Penghu, and submarine cable will be installed by 2014 between Taiwan and Penghu for developing Penghu’s wind farm. The construction of wind generator set have been executed over 10 years in Taiwan, there are have more experience. The effect of monsoon wind is great during the period of assembling and commissioning for wind generator set, in other words, northeast monsoon will make success, or fail. Therefore, work progress shall be arranged according the character of monsoon wind for reducing work period, avoiding work dangerous and improving project efficiency. The optimum schedule of wind generator construction shall consider avoiding northeast monsoon for assembling work, and need strong wind during the period of commissioning test. Therefore, the basic and guiding of whole project arrangement shall be avoiding northeast monsoon in assembling work period, and commissioning test will be executed in northeast monsoon. Construction progress shall be planned for the project successfully regarding the effect of northeast monsoon.
Subjects
Renewable Energy
Wind Energy
Wind Generator Set
Monsoon Wind
Construction Progress
SDGs

[SDGs]SDG7

[SDGs]SDG11

[SDGs]SDG14

Type
thesis
File(s)
Loading...
Thumbnail Image
Name

ntu-100-P97521706-1.pdf

Size

23.32 KB

Format

Adobe PDF

Checksum

(MD5):9e5bc2d337e648b5fb1907bc8b9b481e

臺大位居世界頂尖大學之列,為永久珍藏及向國際展現本校豐碩的研究成果及學術能量,圖書館整合機構典藏(NTUR)與學術庫(AH)不同功能平台,成為臺大學術典藏NTU scholars。期能整合研究能量、促進交流合作、保存學術產出、推廣研究成果。

To permanently archive and promote researcher profiles and scholarly works, Library integrates the services of “NTU Repository” with “Academic Hub” to form NTU Scholars.

總館學科館員 (Main Library)
醫學圖書館學科館員 (Medical Library)
社會科學院辜振甫紀念圖書館學科館員 (Social Sciences Library)

開放取用是從使用者角度提升資訊取用性的社會運動,應用在學術研究上是透過將研究著作公開供使用者自由取閱,以促進學術傳播及因應期刊訂購費用逐年攀升。同時可加速研究發展、提升研究影響力,NTU Scholars即為本校的開放取用典藏(OA Archive)平台。(點選深入了解OA)

  • 請確認所上傳的全文是原創的內容,若該文件包含部分內容的版權非匯入者所有,或由第三方贊助與合作完成,請確認該版權所有者及第三方同意提供此授權。
    Please represent that the submission is your original work, and that you have the right to grant the rights to upload.
  • 若欲上傳已出版的全文電子檔,可使用Open policy finder網站查詢,以確認出版單位之版權政策。
    Please use Open policy finder to find a summary of permissions that are normally given as part of each publisher's copyright transfer agreement.
  • 網站簡介 (Quickstart Guide)
  • 使用手冊 (Instruction Manual)
  • 線上預約服務 (Booking Service)
  • 方案一:臺灣大學計算機中心帳號登入
    (With C&INC Email Account)
  • 方案二:ORCID帳號登入 (With ORCID)
  • 方案一:定期更新ORCID者,以ID匯入 (Search for identifier (ORCID))
  • 方案二:自行建檔 (Default mode Submission)
  • 方案三:學科館員協助匯入 (Email worklist to subject librarians)

Built with DSpace-CRIS software - Extension maintained and optimized by 4Science