Development of an object-oriented scheduling model for construction projects
Resource
Automation in Construction 12, 283–302
Journal
Automation in Construction 12, 283–302
Pages
-
Date Issued
2003
Date
2003
Author(s)
DOI
246246/2006111501244246
Abstract
The relations of the construction activities can be demonstrated by fixed and soft logics. The fixed logic provides only a logic sequence of the construction activities. On the other hand, soft logic provides other possibilities of analyzing the activities. The current network techniques presume that there is only one logical sequence of the activities in a project. Therefore, planners need to choose one particular logical sequence even if there is more than one solution. This causes the time-consuming problem of schedule updating on soft-logic sequencing. This paper discusses the factors that influence the sequencing of the soft-logic and the heuristic sequencing principles. It develops algorithms incorporating with the heuristic sequencing principles to automatically identify the logical sequence of activities with soft logic that satisfies the given factors, and encapsulates the concept in a model with object-oriented paradigm.
Subjects
Scheduling
Soft logic
Object-oriented
SDGs
Publisher
Taipei:National Taiwan University Dept Civil Engn
Type
journal article
File(s)![Thumbnail Image]()
Loading...
Name
7412.pdf
Size
22.97 KB
Format
Adobe PDF
Checksum
(MD5):e2f9f76b3e0e8722439dc020165b9a01