The Research of Earned Value Management for Applications of Construction Project Cost Controlling

Date Issued
2007
Date
2007
Author(s)
Wu, Tsung-ming
DOI
zh-TW
URI
http://ntur.lib.ntu.edu.tw//handle/246246/50231
Abstract
Earned Value management ( EVM ) is a kind of performance measurement system which integrates time and cost. It expresses the achieved of capable achievement by the satisfied work package which is accomplished. Therefore it is an instrument for integrating time, cost and behavior. In America, Australia, Canada, Sweden, England, and Japan, it was used maturely and regards as the best practice of project management. EVM provides three measurement values: planned value, actual value and actual cost of project. These measurement values can help project manager to realize the present condition and provide a conformable measurement value. It can make effective control during the project afoot. This study used EVM, five processes of project construction management, adduced and established cost controlling of project construction management. To make a assessment for benchmark of project’s results and estimate the art of accomplishable efficiency. By using case study to treat the feasibility and meaning of practicing EVM to control project construction management. Per the combination of EVM and statistical control graphs, we can erect achievements audit and evaluate the index’s upper and lower limit. By this way, we can control whole project, to realize the targets: Faster, Better, and Cheaper. Eventually, adopted case study to test above-mentioned, the results are as follow. First, make effective standards performance evaluation and execute efficiency predominate project construction management is successful or fail. Second, combined the index of time, cost, and performance, EVM is the best method. Third, EVM provided crystalline and correct information of project, can predict the effectiveness. Fourth, makes statistics control diagram of project performance for controlling the project, is good for promoting effectiveness of executing project.
Subjects
實獲值
專案管理
專案成本管控
專案績效
Earned value management
project management
cost control of project
performance of project
Type
thesis
File(s)
Loading...
Thumbnail Image
Name

ntu-96-P93521708-1.pdf

Size

23.31 KB

Format

Adobe PDF

Checksum

(MD5):30aa7c203ab99c9a8c597f8a939a8524

臺大位居世界頂尖大學之列,為永久珍藏及向國際展現本校豐碩的研究成果及學術能量,圖書館整合機構典藏(NTUR)與學術庫(AH)不同功能平台,成為臺大學術典藏NTU scholars。期能整合研究能量、促進交流合作、保存學術產出、推廣研究成果。

To permanently archive and promote researcher profiles and scholarly works, Library integrates the services of “NTU Repository” with “Academic Hub” to form NTU Scholars.

總館學科館員 (Main Library)
醫學圖書館學科館員 (Medical Library)
社會科學院辜振甫紀念圖書館學科館員 (Social Sciences Library)

開放取用是從使用者角度提升資訊取用性的社會運動,應用在學術研究上是透過將研究著作公開供使用者自由取閱,以促進學術傳播及因應期刊訂購費用逐年攀升。同時可加速研究發展、提升研究影響力,NTU Scholars即為本校的開放取用典藏(OA Archive)平台。(點選深入了解OA)

  • 請確認所上傳的全文是原創的內容,若該文件包含部分內容的版權非匯入者所有,或由第三方贊助與合作完成,請確認該版權所有者及第三方同意提供此授權。
    Please represent that the submission is your original work, and that you have the right to grant the rights to upload.
  • 若欲上傳已出版的全文電子檔,可使用Open policy finder網站查詢,以確認出版單位之版權政策。
    Please use Open policy finder to find a summary of permissions that are normally given as part of each publisher's copyright transfer agreement.
  • 網站簡介 (Quickstart Guide)
  • 使用手冊 (Instruction Manual)
  • 線上預約服務 (Booking Service)
  • 方案一:臺灣大學計算機中心帳號登入
    (With C&INC Email Account)
  • 方案二:ORCID帳號登入 (With ORCID)
  • 方案一:定期更新ORCID者,以ID匯入 (Search for identifier (ORCID))
  • 方案二:自行建檔 (Default mode Submission)
  • 方案三:學科館員協助匯入 (Email worklist to subject librarians)

Built with DSpace-CRIS software - Extension maintained and optimized by 4Science