  4. Developing a Risk Management Mechanism in the Construction Phase ─ Case Studies on M.R.T. Project
 
  • Details

Developing a Risk Management Mechanism in the Construction Phase ─ Case Studies on M.R.T. Project

Date Issued
2009
Date
2009
Author(s)
Lin, Chi-Hsaun
URI
http://ntur.lib.ntu.edu.tw//handle/246246/187888
Abstract
The life cycle of a construction engineering project includes the phases of planning/ design, construction execution, and completion/operation. Each phase involves its own engineering risk factors. Although efforts are made at each phase to handle the associated risk factors, it is unavoidable that some risk factors are not resolved and needed to be handled at later phases. Currently construction engineering projects in our country tend to suffer most damages from risk factors during the construction phase. When not being handled properly, the situation commonly leads to losses in terms of society unrest, cost increases, longer project duration, or even personnel casualty.urrently most construction engineering companies in our country, that is, those that handle the construction phase, do not possess the skills of managing risk factors. Those companies do not know how to define risk factors, how to identify them, how to assess them, or how to handle and monitor them. As a result, they are unable to proactively control risk factors. They tend to handle risk factors in an ad-hoc fashion and try to make remedies only after unfortunate situations happen. ith that as the motivation, this study, conducted from the perspectives of the construction engineering companies, aims to develop a set of mechanisms for the management of risk factors using the construction phase of the Metro Rapid Transit (MRT) engineering project as an example. It considers the remaining risk factors after the planning/design phase, follows the risk factor management steps in the special project management knowledge system, and is based on the relevant risk factor management documents and the standard management procedure of the MRT Bureau. This study adopts approaches such as expert interview, system analysis, and flowchart construction so as to complete the development of integrated mechanisms that manage the risk factors in both the planning/design and construction execution phases. With the execution of special projects in real environments, it uses individual cases to analyze the operation feasibility of the developed models in practice.ompared to other construction projects, the MRT Construction project involves greater amount of uncertainty in terms of project schedule, engineering environment, and construction conditions. It also covers large urban areas with complicated issues and any derails to the project could have huge impacts. It is sincerely hoped that the integrated risk management mechanisms developed in this study can provide a practical solution to address these risk factors and guarantee the accuracy and effectiveness of the developed M.R.T . Construction risk management model.
Subjects
Project Management
M.R.T. Project
Risk Management
Type
thesis
File(s)
Loading...
Thumbnail Image
Name

ntu-98-P95521715-1.pdf

Size

23.32 KB

Format

Adobe PDF

Checksum

(MD5):02d372f0011d2687ef359f3e587279fc

臺大位居世界頂尖大學之列,為永久珍藏及向國際展現本校豐碩的研究成果及學術能量,圖書館整合機構典藏(NTUR)與學術庫(AH)不同功能平台,成為臺大學術典藏NTU scholars。期能整合研究能量、促進交流合作、保存學術產出、推廣研究成果。

To permanently archive and promote researcher profiles and scholarly works, Library integrates the services of “NTU Repository” with “Academic Hub” to form NTU Scholars.

總館學科館員 (Main Library)
醫學圖書館學科館員 (Medical Library)
社會科學院辜振甫紀念圖書館學科館員 (Social Sciences Library)

開放取用是從使用者角度提升資訊取用性的社會運動,應用在學術研究上是透過將研究著作公開供使用者自由取閱,以促進學術傳播及因應期刊訂購費用逐年攀升。同時可加速研究發展、提升研究影響力,NTU Scholars即為本校的開放取用典藏(OA Archive)平台。(點選深入了解OA)

  • 請確認所上傳的全文是原創的內容,若該文件包含部分內容的版權非匯入者所有,或由第三方贊助與合作完成,請確認該版權所有者及第三方同意提供此授權。
    Please represent that the submission is your original work, and that you have the right to grant the rights to upload.
  • 若欲上傳已出版的全文電子檔,可使用Open policy finder網站查詢,以確認出版單位之版權政策。
    Please use Open policy finder to find a summary of permissions that are normally given as part of each publisher's copyright transfer agreement.
  • 網站簡介 (Quickstart Guide)
  • 使用手冊 (Instruction Manual)
  • 線上預約服務 (Booking Service)
  • 方案一:臺灣大學計算機中心帳號登入
    (With C&INC Email Account)
  • 方案二:ORCID帳號登入 (With ORCID)
  • 方案一:定期更新ORCID者,以ID匯入 (Search for identifier (ORCID))
  • 方案二:自行建檔 (Default mode Submission)
  • 方案三:學科館員協助匯入 (Email worklist to subject librarians)

Built with DSpace-CRIS software - Extension maintained and optimized by 4Science