指導教授:曾惠斌臺灣大學:土木工程學研究所陳宏銘Chen, Hung-MingHung-MingChen2014-11-252018-07-092014-11-252018-07-092014http://ntur.lib.ntu.edu.tw//handle/246246/260876在營建專案工程中,由於其工程之系統種類複雜,以致各系統相互間界面繁多,在施工階段常常因為不完整之界面設計整合,以致造成現場施工產生干涉問題、工期延宕及營建費用增加,使整體工期與品質受到影響。為改善此種情形,本研究將探討系統工程界面設計整合流程步驟,經由已興建營建工程案例,透過蒐集施工所產生之干涉問題,加以歸納整理分析,並探討原有設計整合流程缺失,以尋求合適的設計流程步驟,新增設計整合關鍵指標步驟,以提高設計整合管理的效率,並以一實際之新建營建專案工程案例,進行設計整合流程之研究探討及驗證。 本研究將分為三個階段,第一階段為設計流程探討,以了解各設計部門之間界面關係,第二階段為施工問題產生原因探討,經由案例蒐集歸納,尋求問題關鍵指標,改善系統工程界面設計整合流程,第三階段為將此新增設計整合關鍵指標步驟,套入於興建營建工程案例進行驗證,以確認其可行性。 營建工程由於其系統工程種類複雜以及各系統工程界面繁多,設計管理需要仰賴經驗豐富之工程師,本研究即是將這些經驗條理化與邏輯化,透過改善系統工程界面設計整合流程,施工中經常面臨之問題即可獲得解決,如此,經常發生之變更設計、干涉衝突之問題即可避免,工期與工程品質即可達到如期如質之成果。In the construction engineering project, due to the various engineering types and the system complexity to produce many engineering interface in design and construction stage. During the construction stage is often because they do not complete the integration of interface design, to result the field construction problems and delayed the construction period and the increase in construction costs, and the overall duration and quality is affected. To improve this situation, this study will explore the design integration process steps, via the case by collecting the interference problems arising from constructed engineering project, to collate and analyze existing problem, and explore the lack of original design integration process to seek a suitable process steps, the new design incorporates key index of steps to improve the design of integrated management efficiency, and new construction projects of a practical project case studies designed to explore and validate the integration process. This study will be divided into three stages , the first stage of the design process to probe in order to understand the interface between the design departments, and the second phase of construction problems investigate the reasons summarized by collecting cases seeking control indicator issues, improve system works interface design integration process, and the third stage is the integration of this new design key index steps set into the construction works in construction cases validated to confirm its feasibility. Due to the various construction engineering types and its system complexity and systems engineering interface is multiple, design management need to rely on experienced engineers. In this study, these experiences will be methodized and logical. Interface design through improved integration of systems engineering processes. Construction often face the problem that can be resolved, so frequently occurring changes designed to avoid interference problems of conflict, then schedule and project quality can be achieved the wanted target.口試委員會審定書 # 誌謝 i 摘要 ii ABSTRACT iii 目錄 iv 圖目錄 vi 表目錄 viii 第一章 緒論 1 1.1 研究動機 1 1.2 研究目的 2 1.3 研究範圍與內容 2 1.4 研究方法與流程 3 第二章 文獻回顧 6 2.1 設計管理相關文獻 6 2.2 界面管理相關文獻 9 2.3 小結 17 第三章 營建專案工程設計流程探討 18 3.1 營建工程整合規劃與其流程探討 18 3.2 營建工程規劃設計工作流程探討 21 3.3 營建工程設計圖說工作內容探討 26 3.4 設計圖說界面整合流程探討 47 3.5 小結 63 第四章 設計整合流程問題研究及改善 64 4.1 設計界面施工問題案例蒐集及分析 64 4.2 設計整合案例問題歸納及探討 80 4.3 設計整合案例問題改善及探討 82 4.4 小結 94 第五章 結論與建議 95 5.1 結論 95 5.2 建議 95 參考文獻 96 附錄一 汽電共生廠興建案例設計界面整合問題蒐集資料 998912487 bytesapplication/pdf論文使用權限:不同意授權設計界面設計整合關鍵指標營建專案工程設計界面整合流程探討及改善之研究-以汽電共生廠興建專案為例The Study of Design Interface Integration Process Improvement in Construction Project Engineering-A Case Study of Cogeneration Plant Construction Projectthesishttp://ntur.lib.ntu.edu.tw/bitstream/246246/260876/1/ntu-103-P00521714-1.pdf